What does one bad mobilization really cost?Beta

A crew shows up and can't work: a missing part, no access, the wrong drawings. The wages are the part you see. This calculator follows the miss as it cascades into remobilization, other trades, management time, and schedule recovery, then shows how much of the job's margin it eats. Every price is editable, so set it to your market.

Your job

What's this?

The hourly cost to the shop, not the worker's wage. Includes base wages, payroll taxes (FICA, FUTA/SUTA), workers' comp and liability insurance, health and other benefits, training and certifications, uniforms and PPE, and PTO and holidays. Enter what your shop actually pays.

Customize for your shop (advanced)

These costs are already in the total. Change any number to match your shop. Blank counts as zero.

Your crew

Remobilization repeats 85% of the idle crew labor, not the truck cost. Overtime adds a 50% premium on the lost hours. That is the extra half only, not the full time-and-a-half wage. Change both under Multipliers.

Shop prep
Shop and support overhead

Shop support defaults are placeholders until calibrated. Hours for a role = (crew on site x hours per crew member) + (equipment value / $10,000 x hours per $10,000).

If the foreman is already in the crew size, lower the Foreman row so the same hour is not counted twice. Coordination meetings here are ongoing support, separate from the response meeting below.

Other trades and coordination

The complexity multiplier applies to this layer only. A custom item placed in this layer is included in that multiplier.

This job
Add a cost item

Name the cost, not a person or a company. Item names are stored with the anonymous sample.

Multipliers

Every factor in one place. adjustable assumption except where a field-data tag is shown above.

    Drive hours, prep share, and support role hours are in the sections above. Shop support defaults are placeholders until calibrated.

    The math, line by line

    Not counted: bonding, reputation, cash flow, warranty, morale, and safety. This is a floor, not a ceiling. Estimates are for planning, not accounting.

    Where the default prices come from
    DefaultValueBasis
    Fully burdened labor rate$65/hrAdjustable assumption. A typical shop loaded rate. Includes base wages, payroll taxes, workers' comp and liability insurance, benefits, training, uniforms and PPE, and PTO. Enter yours.
    Truck, fuel, and travel per trip$185Adjustable assumption. 2 trucks x 60 round-trip miles x the IRS business mileage rate of $0.76 per mile (the rate in effect July 1, 2026) is about $91, plus about 1 hour of loading and dispatch at $65 and about $30 for parking or tolls.
    Equipment and storage per idle day$325Adjustable assumption for a lift, a press or threader, and site storage for a day. Enter what you pay.
    Other trades' loaded rate$62/hrAdjustable assumption. Enter the loaded rate for the trade you delayed.
    Meeting average rate$110/hrAdjustable assumption for a mix of PM, superintendent, GC, and owner rep. Documint PM field data uses a range of $50 to $150.
    Overtime premium50%Adjustable assumption. The extra half on top of straight time.
    Remobilization share85%From Documint PM field data. Usual range 75 to 100 percent of idle crew labor.
    Hours lost4From Documint PM field data. Usual range 2 to 8.
    Response meeting3 hrs, 5 peopleFrom Documint PM field data. Hours 2 to 4. People 4 to 8.
    Shop prep share, drive time, support rolesplaceholdersAdjustable assumption. Shop support defaults are placeholders until calibrated.
    ...
    Cost of one bad mobilization
    ...
    Per year
    ...
    Of this job's margin

    Get your cost report

    Your anonymous numbers help us track market pricing. We save the inputs and the total when you get a report, plus optional state, ZIP, and trade. We do not ask for your name, email, or company.

    Optional: state, ZIP, and trade

    How one miss cascades

    Your crew Shop prep Shop and support Other trades Coordination Complexity

    Shop support in this total uses placeholder hours, not a measured study. Open customize to match your shop.

    This calculator is in beta. Tell us what to fix.

    We are still calibrating some defaults, such as shop support hours. If a number looks wrong, something is confusing, or a cost your shop sees is missing, let us know. A screenshot helps.

    Was this useful?
    You can also paste a screenshot into the box above. Once it is added, draw on it to circle the problem.

    Anonymous. We save your rating, your note, the screenshot if you add one, and the numbers on the calculator so we can see what you saw. Please do not type names, and check that the screenshot shows only this page.

    Most bad mobilizations start with something nobody could find.

    A strainer stand that wasn't on the truck, a valve buried in a submittal. Documint PM keeps every spec, RFI, and critical component in one searchable project memory so the crew rolls out with what the job needs.

    See how Documint PM works
    One bad mobilization: ...